← BACK TO NEPHELIS

Project AETHER

A super-pressure balloon probe to the habitable cloud layer of Venus.

NEPHELIS.MCC · PHASE PRE-HARDWARE · LAUNCH TARGET uncommitted — earliest class ~2030–2031+ if gates pass

Why the Cloud Layer?

Between 50 and 60 kilometers above the surface of Venus lies a region with Earth-like temperatures (0–60°C) and pressure (~1 atm). This is the only place in the inner solar system, besides Earth itself, where humans could potentially live without extreme life support.

Mission Concept

AETHER will deploy a long-duration super-pressure balloon carrying a suite of instruments for atmospheric sampling, imaging, and in-situ analysis. The probe will float for weeks or months, providing unprecedented data on this unique environment.

Probe specs

  • Type: Super-pressure balloon
  • Altitude: 5060 km
  • Temperature: 060 °C
  • Instruments: Atmospheric spectrometers, High-res cameras, Meteorological suite, Life detection experiments
  • Wet mass class: ~400 kg · balloon ~6.6 m

Mass budget (summary)

ElementMass (kg)
Kick / transfer stage (wet)330380
Entry probe + balloon + gondola (dry stack)150200
Heatshield / blunt-body base5060
Fluoropolymer balloon + inflation3545
Gondola + sensor suite4055
Avionics, power, structure, comms2535

Positive headroom vs 400 kg wet — acid protection, helium, redundancy

Mission control checklist

  • in_progressGitHub ehreng/Nephelis as single source of truth with open L1–L3 issues2026-Q3
  • in_progressKeep /status and progress.json current with built vs not-yet2026-Q3
  • in_progressMission requirements baseline (v0.9 draft exists — keep honest about incompleteness)2026-Q4
  • plannedCONOPS updated for ground-first program (flight dates aspirational)2026-Q4
  • plannedAcid / materials coupon campaign started (first coupons + log photos)2027-H1
  • plannedSmall helium ground float prototype with basic telemetry2027
  • in_progressRegulatory path notes (FAA/FCC/export) drafted publicly2026-Q4
  • plannedLive payment rails OR honest “not open yet” state (no fake allocation)2026-Q4
  • planned50% of $500k ground-campaign goal committed (if fundraising opens)2027+
  • plannedFlight program gate: only after ground demonstrator success + credible capital plan2028+

Top open risks

RISK MATRIX · OPEN / MITIGATING
likelihood →impact →01020304050607
  • R-01 Acid degradation of balloon envelope
  • R-02 Entry / inflation sequence failure
  • R-03 Comms blackout / insufficient downlink
  • R-04 No committed launch path; schedule risk is structural
  • R-05 Capital shortfall vs flight-class cost
  • R-06 Planetary protection / DNA tier regulatory delay
  • R-07 Sensor mass growth eats float margin
  • R-01 Acid degradation of balloon envelope (high/medium) — Multi-layer fluoropolymer; altitude selection; coupon protocol in docs/materials-coupon-test-protocol.md
  • R-02 Entry / inflation sequence failure (critical/medium) — Redundant inflation path; extensive drop / vacuum tests; VEGA lessons
  • R-03 Comms blackout / insufficient downlink (high/medium) — 3U CubeSat relay architecture; store-and-forward; power budget margin
  • R-04 No committed launch path; schedule risk is structural (high/high) — Gate flight talk on ground demonstrator success; explore rideshare after hardware gates; plan for 2030s-class transfer windows
  • R-05 Capital shortfall vs flight-class cost (high/high) — $500k framed as ground/prototype campaign only; Stripe not yet live; partner in-kind; honest fundraising copy

Full register in data · public roadmap at /roadmap.

Data-driven from mass-budget.json, mission-control.json, risks.json, specs.json, power-budget.json.